Projects
Services
One of the leading manufacturers and distributors of gases in the Middle East.
About us
Corporate Brochure
We work to serve diverse industries, from petrochemicals to laser cutting, meeting your demands to help you compete in the market.
Industries We Serve
Know More
Our highly skilled engineers work with our clients to develop technologies to advance processes and techniques through innovative gas applications, finding the best solution for you.
Healthcare
Gulf Cryo provides a complete end to end solution for medical gas applications, including storage, engineered delivery system and secondary equipment and accessories.
Pre-Hospitals
Hospitals
Industrial Gases
Medical Gases
Markets
Specialty Gas Facility
We offer various services and technological solutions, ranging from pH control solutions to laser cutting to purging jobs.
Technologies
We are committed to protecting our team and the environment by adhering to safety standards under our SHEQ management system.
Gas Supply & Management
Our production facilities, wide variety of gas and process management programs, and delivery systems are all designed to help get you the gas you need.
Air Separation Plant, Sulaimaniyah, Iraq
Relocation of 55TPD Air Separation Plant from Dubai to Sulaimaniya, Northern Iraq to serve Northern Iraqi Markets. The Product from this plant will cater to the major clients like hospitals, engineering industries, and manufacturing sectors like steel, cement, oil fields and refineries. This illustrates GC’s keen interest to expand its markets presence and cater to its clients with its value added products and services.The Plant had been successfully dismantled, Packed and safely shipped to Project Location in Sulaimaniyah. From the beginning of the Project Construction Phase in Aug 2016, there has been substantial achievements in accomplishing the construction activities as per the schedule despite many challenges including crucial weather conditions. Mechanical completion achieved in June 2017 and Plant energized in August 2017. However, the Plant commissioning delayed due to the ban imposed after Kurdistan Independence Referendum.
Plant commissioning is achieved in the beginning of July 2018. There were a lot challenges faced during Construction and Commissioning activities. However, the overall project completed on Budget (Project Value USD 8.5 Million. It is one of the major achievement of this project.The project and operations team has achieved a `ZERO-ZERO' safety record with 119,500man-hours worked.